ICS 125 - Team 7

Log

Log 5

Friday, March 3, 10:00 pm

Team 7 continued finishing up solution 1 GUI and working on solution 2 code. Code iteration 3 was sent to Amir and posted on the website

Monday, March 6, 3:00 pm

Team 7 continued programming solution 2 and finished solution 1

Tuesday, March 7, 5.00 pm

No Lecture, Team 7 meets with the customer and presented the current progress

Tuesday, March 7, 6.30 pm

Team 7 meet up at ICS 193 to continue programming on solution 2. Started to revise the Final Design Iteration and updated the Final Requirement.

Wednesday, March 8, 3:00 pm

Team 7 continued programming on solution 2. Finished presentation material for the Final Presentation

Thursday, March 9, 6.30 pm

Meeting with Eric to discuss about the appraches taken for solution 2 and GUI

Friday, March 10, 12:00 am

Made some changes with the GUI for solution 2 and working on solution 2. Worked on final test iteration

Monday, March 13, 11:50 pm

Submitted Final Test Iteration with results

Tuesday, March 14, 3:00 pm

Team 7 finished with solution 2 and final design & final requirement document

Wednesday, March 15, 5:00 pm

Meet with Yang Wang and presented the final demo to him. Customer was satisfied and made some last minute suggestions

Thursday, March 16, 12:00 pm

Eric sent an email about last minute notices to do. Team 7 meets to tackle the problem. Team Log 5 is finished and subjective assesments are finished

Thursday, March 16, 6.:30 pm

Team 7 practice for the final demo milestone the next morning. Final delivery of final documents.

 